Community Notifications
Track maintenance works on the Seymour Line
Seymour line
V/Line crews will carry out renewals works at Beveridge Road and Minton Steet level crossing.
Works schedule
Tuesday 8 and Wednesday 9 September – 10pm – 6am
Friday 11 to Thursday 17 September – 7am – 5pm
What to be aware of
There will be a high level of construction noise at times, as crews replace and tamp ballast.
There will be regular movement of heavy machinery and trucks, and a significant amount of dust is expected at the work site.
The work site will be accessed via Beveridge level crossing. There will be localised traffic management in place as required. Please allow extra time when moving through the area.
We thank you for your understanding while these important maintenance works take place.
For more information, please call 1800 800 007.